Dear Joe,
about the VIR documentation lien resolution status, I've no updates
currently.
About the VIR CSL data deliveries, we're working on a delivery plan that
should be out during this week.
Best regards,
Marco
Il 24/02/2016 23:32, Joseph Mafi ha scritto:
> Hi Folks,
>
> We'll hold a DAWG telecon tomorrow. Topics for discussion include the
> FC instrument kernel, and VIR documentation lien resolution status.
> Please provide updates by email if you are unable to attend
>
> Thanks,
> joe
> .
>
>
>
> Link to meeting WebEx:
> https://jplwebex.jpl.nasa.gov/orion/joinmeeting.do?ED=kT5hGvk3Vprdug3ERfURng==
>
>
> Direct dialing information:
> Call into JPL WebEx: 818-35(4-4044) or Toll Free 844-JPL-WEBX
> (844-575-9329)
> Meeting Number: 999 257 391
>
>
> Delivery Schedule
> =================
> Data Due to DSC Due to PDS
> ------------ ---------- ----------
> VCC L-1A 2015-03-26 2015-04-01
> CSA/CSR L-1A 2015-06-26 2015-07-10
> CSA/CSR L-1B 2015-07-27 2015-08-10
> CTS/CSS L-1A 2015-08-18 2015-09-01
> CTS/CSS L-1B 2015-09-17 2015-10-01
> CTH/CSH L-1A 2015-11-10 2015-11-30
> CTH/CSH L-1B 2015-12-28 2016-01-11
>
>
> Archive Delivery Status
> =======================
> * Ceres coordinate system- Kait-centered coordinate system
> approved. Coordinate system description paper must be updated prior to
> release.
> * FC
> * Ceres Approach/RC3 L-1A volume in lien resolution (Oct 2015)
> - Certified with liens; released (Oct 2015)
> * pre-Vesta L-1A and L-1B volumes in lien resolution
> - Certified with liens (May 2014)
> * Calibration volumes: FC1 certified; FC2 in peer review (Sep
> 2015)
> * GRaND
> * Ceres cruise L-1A delivered to PDS; review delayed (Aug 2015)
> * Ceres Approach/RC3 L-1A volume delivered to PDS; L-1B
> volume in prep; peer review delayed (Aug 2015)
> * Vesta L-1B volume in lien resolution (2014)
> * Mars L-1B liens resolved; volume archived (Jul 2015)
> * VIR
> * Ceres Approach/RC3/Survey L-1A volumes (excluding Survey IR
> volume) in lien resolution (Oct 2015)
> - Certified with liens; released (Oct 2015)
> * Ceres Approach/RC3 L-1B volumes in peer review (Sep 2015)
> * Cruise L-1A and L-1B volumes in lien resolution (Jul 2015)
> * Vesta high level product volumes in preparation (Dec 2014)
> * Vesta L-1B recalibrated data in preparation (UNK)
> _______________________________________________
> Dawndawg mailing list
> Dawndawg at igpp.ucla.edu
> http://lists.igpp.ucla.edu/mailman/listinfo/dawndawg
More information about the Dawndawg
mailing list