Archive Delivery Status
=======================
* Ceres coordinate system- Kait-centered coordinate system approved.
Coordinate system description paper must be updated prior to release.
* FC
* Ceres Approach-HAMO L-1A & L-1B: delivered to PDS; ready for
review (Apr 2016)
* Ceres Approach/RC3 L-1A: delivered to PDS; liens resolved;
new data (calibration images) ready for review;
* pre-Vesta cruise L-1A & L-1B: delivery to PDS pending
* Calibration volumes: delivery to PDS pending
* Ceres HAMO L-2 global mosaics - delivered to PDS; ready for
review
* GRaND
* Ceres cruise L-1A: certified with liens; in lien resolution;
(Apr 2016)
* Ceres Approach/RC3/HAMO L-1A & L-1B: certified with liens;
in lien resolution; (Apr 2016)
* VIR
* Ceres Approach/RC3/Survey L-1A: (excluding Survey IR volume)
liens resolved; archived
* Ceres Approach/RC3 L-1B: liens resolved; archived
* Ceres Survey - HAMO L-1A & L-1B: delivered to PDS; ready for
review (Apr 2016)
* Cruise L-1A & L-1B: delivery to PDS pending
* Vesta L-1A (updated HK tables): delivery to PDS pending
* Vesta L-1B (new calibration): delivered to PDS; minor
documentation updates required
* Vesta L-2: delivery to PDS pending
* Shape Model
* Gravity team: Updated volume delivered to DSC; delivery to
PDS pending (Apr 2016)